Parking of Galileo Shopping Center

  • Completion date
    October 2023
  • Project type
    Waterproofing

The most problematic areas at different levels of multi-level parking were repaired locally – the passage of utilities, the junction of floor slabs to columns and walls, repair of the storm system with the replacement of rainwater funnels. The work was carried out in the conditions of an existing parking with high vehicle traffic.

In a short time, the floor pie was opened, repair work was carried out and the paving slabs were restored.

Work completed

Repair of old waterproofing

One of the tasks during local repairs of the waterproofing system is to ensure the joint operation of the new and old waterproofing. In this project, MB 2K reactive material was used, which ensured the hermetic connection with the old bitumen waterproofing.

Sealing of utility inputs

The tightness of utility passages was ensured by using Remmers Stopaq polyurethane sealant followed by MB 2K coating.

Repair of drainage systems, roofs
Water drainage funnels were replaced with two-level ones, and a drainage layer was added, which allowed not only to collect water from tiles and waterproofing, but also to gradually drain water from previously soaked layers.